Ask a stakeholder how the budget looks, and you'll get one of two questions back. Either "how much will this cost in total?" or "how much more do we need?"

Those are not the same question. And on the PMP exam, picking the wrong one costs you the point — even if your math is perfect.

Two different questions

  • EAC (Estimate at Completion) — total project cost, forecast to the end.

  • ETC (Estimate to Complete) — cost of the work still remaining, from today forward.

EAC

ETC

Answers

What will this project cost in total?

What's left to spend from here?

Includes past spend

Yes (AC is built in)

No — forward-looking only

Core formula

Four variants, depending on assumption

ETC = EAC − AC

Used when

Forecasting final cost

Re-planning remaining work

Get the question wrong, and you'll answer with the wrong number even if every calculation along the way is correct.

The abbreviations

The formulas below use five variables. Keep these straight before anything else:

  • PV — Planned Value. The budget authorized for the work planned to be completed to a point in time — usually the data date, meaning the specific day project performance is being measured.

  • EV — Earned Value. The budgeted value of the work completed to the data date.

  • AC — Actual Cost. What was actually spent on the work completed to the data date.

  • BAC — Budget at Completion. The sum of all budgets for the work to be performed. This total is also known as the project's cost baseline.

  • CPI — Cost Performance Index. EV / AC — how efficiently money is being spent.

The four EAC formulas

EAC isn't one formula. It's four, each tied to a different assumption about what happens next:

How it is used

Formula

If the CPI is expected to stay the same for the rest of the project, use this to calculate EAC

EAC = BAC / CPI

If future work will be completed at the planned rate, use this to calculate EAC

EAC = AC + (BAC − EV)

If the original plan is no longer valid, re-estimate the remaining work one task at a time

EAC = AC + Bottom-up ETC

If both CPI and SPI are expected to influence the remaining work, use this to calculate EAC

EAC = AC + [(BAC − EV) / (CPI × SPI)]

The exam signals which one applies through wording, not through a formula prompt. "CPI expected to stay the same" points to BAC/CPI. "No longer valid" points to bottom-up ETC. Miss the phrase, and you'll reach for the wrong equation.

How they connect

Once EAC is set, ETC follows directly:

ETC = EAC − AC

That's the standard relationship — assuming work continues as planned. But when the original baseline no longer holds, ETC gets re-estimated one task at a time instead. That's the same trigger that drives the third EAC formula above. The two aren't calculated independently — a bottom-up ETC feeds directly into EAC.

A realistic scenario

BAC is $500,000. At the midpoint, EV is $200,000, AC is $250,000. Cost performance is expected to continue at the current rate.

"Expected to continue" is the signal — use EAC = BAC / CPI.

CPI = EV / AC = 200,000 / 250,000 = 0.8 EAC = 500,000 / 0.8 = $625,000 ETC = EAC − AC = 625,000 − 250,000 = $375,000

Change the scenario to "the original estimate is no longer considered valid," and both numbers shift — EAC now comes from a bottom-up ETC instead. Same project, different assumption, different answer.

How to prepare for this

  • Read the scenario for the assumption first — name the formula before touching a calculator

  • Practice the relationship, not just the arithmetic: EAC first, ETC follows

The takeaway

EAC and ETC aren't two formulas to memorize. They're two questions a stakeholder is actually asking. Know which one is being asked, and the right formula — and the right number — follows on its own.

P.S. Planning your ECO 2026 study plan? The PMP Study Plan Calculator breaks it down by domain weights and available study time: https://vandersonbaril.com/products/pmp-study-calculator/

I would also be interested to hear where you are in your own PMP journey. While I may not be able to respond to every message, I do read all replies.

Thanks for reading, and see you next Saturday.

Keep Reading